Sunday, June 7, 2009

MB raps PWD over shoddy job on aquatic complex

KUALA TERENGGANU: The failure of the state Public Works Department (PWD) to oversee the construction of the Batu Burok Aquatic Complex here and subsequently failing to conduct periodic checks on the completed sporting facilities has drawn flak from Mentri Besar Datuk Ahmad Said.

Ahmad, who made a surprise visit to the complex yesterday, was visibly upset when he discovered numerous defects in the structure of the RM18mil building.

“Since day one, the PWD should have scrutinised the construction. The roof is leaking and water is lying stagnant in several parts of the building,” he said.

Ahmad said the PWD engineers should have checked on the materials used for the construction of the complex as its proximity to the beachfront meant the materials should be able to withstand adverse weather.

He said the PWD engineers and architects should have been more responsible by conducting constant checks from the start of the construction until the completion.

“They should also have taken into account the cost of the maintenance of the complex if the building materials were not according to specification; this oversight has resulted in imprudent expenses for the state.”

Ahmad was also disappointed to see that the steel pillars supporting the canvas roof at the complex had corroded after just one year.

“The pillars in the complex should have been coated with anti-rust.

“And, luckily, this roof is made of canvas or else we could have another incident of a roof collapsing in the state,” he said, adding that he would call for immediate remedial works.

Meanwhile, Terengganu Swim-ming Association secretary Yan Kong Lee said the defects at the stadium were actually reported to PWD last year.

He added that the leaks in the roof had also damaged facilities and computers at the office inside the aquatic centre.Star

Former exco man: Opposition merely looking for a scapegoat

KUALA TERENGGANU: Former state executive councillor Datuk Wan Hashim Wan Salleh blasted Opposition leaders here for blaming the state government over the collapse of Sultan Mizan Zainal Abidin Stadium’s roof.

Wan Hisham, who previously helmed the Infrastructure, Public Amenity and Communi-cation committee under former Mentri Besar Datuk Seri Idris Jusoh, said: “They are just looking for a scapegoat. This is definitely unethical.”

Opposition leaders should wait for the outcome of the probe into the mishap before pointing fingers at others, he said yesterday.

He was commenting on a statement by state PAS deputy information chief Dr Alias Razak who said the state government had responded lackadaisically to complaints brought up last year on the flaws spotted on the roof frame of the stadium.

“It is the norm for the Opposition to pin the blame on the state government for every single thing,” he said.

“Previously, they faulted us even on issues like the under-performance of students. This is their way of scoring political mileage.”

Wan Hisham also urged the Public Works Department to investigate the collapse from all aspects including engineering, design and construction of the structure.

Tuanku Mizan upset with stadium incident, says MB

KUALA TERENGGANU: Yang di-Pertuan Agong Tuanku Mizan Zainal Abidin is disappointed over last Tuesday’s roof collapse of the stadium in Gong Badak named after him.

Mentri Besar Datuk Ahmad Said, who sought an audience with the King to brief him about the mishap, said Tuanku Mizan was unhappy with the incident.

Ahmad met Tuanku Mizan on two occasions, once on the same day the mishap occurred; and again Friday when he produced photographs of the devastation at the stadium.

“His Highness seemed sad and disappointed over the mishap,” he said after accompanying police on a crime prevention round at the city centre on Friday night.

Tuanku Mizan had opened the RM300mil stadium, with a seating capacity of 50,000 on May 10 last year — just weeks before Terengganu hosted Sukma 2008.

The stadium is touted to be the biggest in the east coast and was the first in Asia to be equipped with a roof shaped like a turtle.

Ahmad said Tuanku Mizan was also upset with the extent of damage at the stadium.

He said the state is willing to make public the outcome of the probe conducted by Public Works Department.

“We will release the final report so that those responsible (in the construction and maintenance) will not be able to repeat such blunder.”

Ahmad said the state is ready to help the Malaysian Anti-Corruption Commission in its probe into the collapse.

“So far, the commission has not contacted me or my officers on this, but we will be transparent and divulge all crucial information regarding the stadium if we are asked to do so.”

Wednesday, June 3, 2009

Bumbung Stadium Runtuh Tiada Sijil Siap Kerja - JKR

KUALA TERENGGANU, 3 Jun (Bernama) -- Bumbung Stadium Sultan Mizan Zainal Abidin dekat sini, yang runtuh pagi semalam tidak memiliki Sijil Siap Kerja yang dikeluarkan Jabatan Kerja Raya (JKR).

Timbalan Pengarah Kerja Raya Negeri, Ghazali Hashim mengesahkan perkara itu dan berkata bumbung berkenaan adalah antara kemudahan di stadium tersebut yang belum diberikan sijil tersebut.

Mengikut amalan kerja, katanya JKR akan mengeluarkan Sijil Siap Kerja terhadap bangunan milik kerajaan yang sudah siap dibina.

"Hanya kemudahan seperti trek, padang selain beberapa tempat di luar stadium telah diberikan sijil itu. Sijil ini telah dikeluarkan semasa penganjuran Sukan Malaysia (Sukma) pada 31 Mei tahun lepas.

"Bumbung stadium masih belum diberikan sijil tersebut kerana masih dalam tempoh kecacatan (jaminan)," katanya ketika ditemui selepas mengiringi Menteri Belia dan Sukan Datuk Ahmad Shabery Cheek meninjau stadium berkenaan hari ini.

Ghazali berkata sebelum ini, jururunding yang dilantik telah memaklumkan kepada JKR bahawa bangunan stadium berkenaan sudah siap.

"Bagaimanapun, kita masih menunggu komen daripada pihak kontraktor berhubung keupayaan struktur bumbung stadium itu sebelum mengeluarkan sijil ini," katanya.

Berikutan insiden runtuhan itu, beliau berkata pihaknya akan berurusan dengan kontraktor utama stadium tersebut dan bukannya syarikat kontraktor dari Korea Selatan yang merupakan subkontraktor dan bertanggungjawab memasang bumbung tersebut.

Dalam perkembangan berkaitan, katanya stadium berkenaan dijangka ditutup selama enam bulan bagi membolehkan siasatan terhadap insiden runtuhan itu dijalankan.

Beliau berkata dalam tempoh itu, kerja-kerja membersih dan membaik pulih stadium berkenaan juga tidak akan dilakukan.

-- BERNAMA

Konsultan bebas siasat punca runtuhan stadium

KUALA TERENGGANU – Kerajaan negeri akan melantik konsultan bebas bagi menyiasat punca runtuhan bumbung bangunan Sta-dium Sultan Mizan Zainal Abidin dalam kejadian di Gong Badak, di sini, semalam.

Menteri Besar, Datuk Ahmad Said berkata, pihaknya sedang mengenal pasti konsultan terbabit berdasarkan kepakaran menyiasat kejadian itu.

“Selain Jabatan Kerja Raya (JKR), kita akan lantik satu lagi konsultan bebas yang betul-betul boleh di-percayai dari segi kepakaran menyiasat kenapa ini ter-jadi,” katanya kepada pem-berita ketika ditemui di lokasi runtuhan bangunan, semalam.

Ditanya berhubung punca runtuhan, Ahmad enggan mengulas dan menyerahkan kepada pakar sambil memaklumkan stadium itu akan ditutup sehingga kerja baik pulih selesai.

Berhubung bumbung Bahagian Timur yang rosak teruk dalam runtuhan itu, Ahmad berkata, kontraktor dari Korea bertanggungjawab terhadap pembinaan bumbung berkenaan.

“Bumbung bahagian itu lebih tinggi dan besar dengan 200 meter panjang berbanding bahagian sebelah barat yang tidak mengalami sebarang kerosakan.

“Pembinaan bumbung kedua-dua bahagian itu mencecah RM38 juta, se-mentara kerugian yang ter-paksa ditanggung untuk kerosakan itu adalah RM25 juta,” katanya.

Bagaimanapun, menurut Ahmad, pihaknya akan turut memberi perhatian kepada bumbung bahagian barat bagi memastikan keadaan terkawal.

“Kerugian akan ditanggung kontraktor berikutan tempoh kecacatan belum berakhir,” katanya.

Runtuhan bumbung di Stadium Sultan Mizan Zainal Abidin berlaku pada jam 9.30 pagi membabitkan hampir keseluruhan bahagian timur ('East Stand') yang turut menempatkan kawasan tempat duduk golongan diraja dan kenamaan.

Kejadian itu turut mengakibatkan 19 orang terperangkap iaitu pekerja di pusat boling dan dua tukang cuci, namun kesemuanya disahkan terselamat serta tidak mengalami kecederaan.

Stadium Sultan Mizan Zainal Abidin yang dibuka tahun lepas dianggarkan bernilai RM292 juta termasuk kemudahan sekitarnya mampu memuatkan sehingga 50,000 penonton. Sinar

Konsultan bebas siasat punca runtuhan stadium

KUALA TERENGGANU – Kerajaan negeri akan melantik konsultan bebas bagi menyiasat punca runtuhan bumbung bangunan Sta-dium Sultan Mizan Zainal Abidin dalam kejadian di Gong Badak, di sini, semalam.

Menteri Besar, Datuk Ahmad Said berkata, pihaknya sedang mengenal pasti konsultan terbabit berdasarkan kepakaran menyiasat kejadian itu.

“Selain Jabatan Kerja Raya (JKR), kita akan lantik satu lagi konsultan bebas yang betul-betul boleh di-percayai dari segi kepakaran menyiasat kenapa ini ter-jadi,” katanya kepada pem-berita ketika ditemui di lokasi runtuhan bangunan, semalam.

Ditanya berhubung punca runtuhan, Ahmad enggan mengulas dan menyerahkan kepada pakar sambil memaklumkan stadium itu akan ditutup sehingga kerja baik pulih selesai.

Berhubung bumbung Bahagian Timur yang rosak teruk dalam runtuhan itu, Ahmad berkata, kontraktor dari Korea bertanggungjawab terhadap pembinaan bumbung berkenaan.

“Bumbung bahagian itu lebih tinggi dan besar dengan 200 meter panjang berbanding bahagian sebelah barat yang tidak mengalami sebarang kerosakan.

“Pembinaan bumbung kedua-dua bahagian itu mencecah RM38 juta, se-mentara kerugian yang ter-paksa ditanggung untuk kerosakan itu adalah RM25 juta,” katanya.

Bagaimanapun, menurut Ahmad, pihaknya akan turut memberi perhatian kepada bumbung bahagian barat bagi memastikan keadaan terkawal.

“Kerugian akan ditanggung kontraktor berikutan tempoh kecacatan belum berakhir,” katanya.

Runtuhan bumbung di Stadium Sultan Mizan Zainal Abidin berlaku pada jam 9.30 pagi membabitkan hampir keseluruhan bahagian timur ('East Stand') yang turut menempatkan kawasan tempat duduk golongan diraja dan kenamaan.

Kejadian itu turut mengakibatkan 19 orang terperangkap iaitu pekerja di pusat boling dan dua tukang cuci, namun kesemuanya disahkan terselamat serta tidak mengalami kecederaan.

Stadium Sultan Mizan Zainal Abidin yang dibuka tahun lepas dianggarkan bernilai RM292 juta termasuk kemudahan sekitarnya mampu memuatkan sehingga 50,000 penonton. Sinar

Tuesday, June 2, 2009

RM80,000 untuk tiga sekolah

KEMAMAN 31 Mei - Anak syarikat kerajaan negeri, Eastern Pacific Industrial Corporation Berhad (EPIC) menyumbang sejumlah RM80,000 kepada tiga sekolah elit dan premier di daerah ini bagi membantu meningkatkan tahap pendidikan di sekolah itu.

Sekolah yang terlibat ialah Sekolah Menengah Kebangsaan (SMK) Mak Lagam, SMK Premier Chukai dan SMK Kijal.

Pengurus Komunikasi Korporat EPIC, Wan Ahmad Wan Sudin berkata, sumbangan tersebut bertujuan membantu sekolah melaksanakan program nilai tambah untuk para pelajarnya yang bakal menghadapi peperiksaan utama tidak lama lagi.

"Ini adalah program pertama EPIC yang bertujuan membantu mengembangkan tahap akademik di setiap sekolah.

''Kita ingin melihat anak-anak Terengganu terus mencapai keputusan cemerlang dalam Penilaian Menengah Rendah (PMR) dan Sijil Pelajaran Malaysia (SPM)," katanya kepada pemberita selepas merasmikan majlis EPIC Gemilang PMR dan SPM di SM Mak Lagam di sini kelmarin.

Dalam pada itu, Pengetua SMK Mak Lagam, Nong Shamsiah Mokhtar Affandi berkata, pihaknya berterima kasih kepada EPIC kerana sudi membantu sekolahnya dan beberapa sekolah yang lain. - Utusan